ANM9 / 14 / 4 



----- Original Message ----- 
From: Lialios Asterios 
To: iala-aism@wanadoo.fr 
Sent: Monday, March 26, 2007 9:14 AM
Subject: Lighthouse specifications


Dear Sirs,

 

Hellenic Petroleum Elefsis Refinery is currently considering a project on the construction of a new lighthouse on the edge of one of its existing Piers. The refinery has two piers for loading and unloading crude oil and products to vessels up to 350,000 MT DWT. The Pier I in question can receive vessels up to 80,000 MT DWT.

We kindly request any available recommended technical specifications on the lighthouse in question in order to proceed with the project according to IALA specs. Naturally, we remain at your disposal for any clarifications required.

 

Regards,

 

A.Lialios

Operations Engineer

Oil Movement Dept.

Hellenic Petroleum- Elefsis Refinery

 